Basic Information - Industrial Sales of Oakland Manufacturer of quality Collet Pads and Top Jaws
Extra-large collet, in pieces

 

Comparison Chart for Different Systems

Averages based on one machine in one shop. 

  Manual Machining Collet Systems Top Jaw System
Time to Change 30 minutes 5 minutes 3 minutes
Cost Per Hour $60.00 $60.00 $60.00
Total Cost/Change $30.00 $5.00 $3.00
Avg. # Changes/Week 20 10 20
Collet System Mounting - 2x/week $120.00 -
Total Cost per Year $31,200 $6,240 $3,120

Startup costs for these three methods vary, but for a one year run tooling costs for each generally run as follows:

  • Manual Machining:  $30-$90, continuous cost
  • Collet System:  $2,500-$5,000, one time purchase
  • Top Jaw System:  $495-$750, one time purchase

 

 

Industrial Sales of Oakland • 74 Snyder • Lake Orion, MI 48362 • 1.800.628.5621 • fax: 248.693.3096

Site design by amdove Design
DHTML navigation provided by Milonic